Submitted on 13 November 2020

Rupees in crores


Project Name

Project Cost

Project status

Mode of Implementation

Expenditure incurred till FY 2020

FY 2021
(Actual)

FY 2021
(Projected)

FY 2022

FY 2023

FY 2024

FY 2025

Physical Progress

Financial Progress

Source of Funding PPP/State/Central support/others

Project Details / Status

Reconstruction of SCB at Cochin Port for Handling Chemicals

19.19

Under implementation

EPC
Contract

Nil

0.37

3.27

15.92

Nil

Nil

Nil

Nil

Nil

Central support

In progress

Developing Additional Infrastructure for New Cochin Port Cruise Terminal

10.30

Under implementation

Percentage Basis Contract

Nil

2.44

6.57

3.73

Nil

Nil

Nil

52%

23.70%

Central support

In progress

 

Project Name

Project cost

Project Status

Mode of Implementation

Financial Progress

Physical Progress

Source of  Funding

Project Details/Status

Development of International Ship Repair Facility (ISRF) at Willingdon Island under Private Sector Participation

Rs.970 cr

Work in progress

Lease Model with Revenue Share
 

65.9

74.5%

M/s.CSL  own Source

This is a continuing project started on 09-01-2018.  Overall completion date of project is 09-01-2023.

Installation of 2 MW of Solar Plants.

Rs.9 Crores

Yet to be started

Ministry of Port Shipping and Waterways Sagarmala

Nil

Nil

Ministry of Port Shipping and Waterways, Sagarmala

There is a proposal to provide floating solar panels at Puthuvyppin area with the request from Sagarmala..

 Up gradation of power supply distribution and  Automation in feeder/distribution  system at Vallarpadam Substation as per the PPP operator and IOCL  for their additional load requirement.

Rs. 5 Crores

Yet to be stared

Funded by PPP operators

Nil

Nil

Funded by PPP operators

As per the PPP operators’ requirement

Shore supply to cruise vessels  berthed at port.

Rs. 10 Crores

Yet to be started

Ministry of Port Shipping and Waterways,Sagarmala

Nil

Nil

Ministry of Port Shipping and Waterways, Sagarmala

By providing power supply to cruise vessels, carbon foot printing can be reduced.

Replacing of conventional  lamps fittings with LED fittings

Rs.60 lakhs

Commenced

Internal source/Funds from Tourism master plan

30%

30%

Internal source/Funds from Tourism master

Replacing conventional lights with LED is a part of the Tourism Master Plan to transform Willingdon Island into a Tourism Hub.

Last updated :: 08/02/2021, -10:46

Cochin Port handles Chemical Products like Liquid Ammonia, Methanol, Ethylene Dichloride (EDC) etc. , at two berths. One of the berths is called South Coal Berth (SCB), which was commissioned in the year 1953. Till very recently, the berth was used for handling liquid ammonia of Fertilizer & Chemicals Travancore Limited (FACT, a Government of India Undertaking) and their liquid storage tanks near the berth are spread over an area of 1 hectare.

The SCB is in a damaged condition due to ageing and corrosion. As the structure is beyond economical repairs and also outlived its economic life, a Health Check-up Study was got conducted by M/s. National Technological Centre for Ports, Waterways & Coasts (NTCPWC, IIT, Madras), the extended arm of Ministry of Shipping, and they have recommended demolition and reconstruction the SCB to meet the durability and strength requirements. As such, it is proposed to reconstruct SCB to facilitate handling of chemicals.

The proposed reconstruction of SCB consists of: (i) Construction of Berthing Jetty  of size 110m x 12m on 1000mm dia piles founded at -37m CD; (ii) Construction of Approach Trestle of size 48m x 7mon 800mm dia piles founded at -37m CD; (iii) Demolition of Existing Jetty including cutting piles, to the extent required for construction of the proposed structures;  (iv) Laying Concrete Road to Approach Trestle;  and (iv) Electrical works consisting  of modification to the existing 11 KV distribution system to providelighting on the Berth and Approaches Trestle etc.  The Berthing Structure is designed for a vessel of maximum size of 35,000DWT, 9.14m draft, 183.6m LoA and 27.60m beam.

 

 

"SCB"

The total estimated cost of the Project works out to about Rs.19.19 Crores. MoS on 13/12/2029 conveyed the in-principle approval of Competent Authority of MoS for funding 50% of Project Cost/ Tendered Cost, which ever is less, under Sagarmala Scheme. Out of the balance, 25% will be advanced by the main user agency viz., M/s. FACT (amount to be adjusted against future wharfage / berth hire charges) and the remaining 25% will be shared by CoPT.  The Project Cost is revised to Rs. 20.90 Crores on preparation of detailed estimate after preliminary design by the consultants, NTCPWC..

The Project is expected to be implemented within a period of 17 months. As before, the reconstructed SCB will also be operated and maintained by Cochin Port Trust. 

The work of "Re-Construction of South Coal Berth at Cochin Port on EPC Contract Basis" has been awarded to the contractors M/s KVJ Builders & Developers Pvt. Ltd., Kochi a contract value of Rs.17,70,55,267.50 on 19/11/2020. The work is commenced on 26/11/2020 and in progress.

The Hon’ble  Prime Minister of India laid foundation stone of the project on 14-02-2021. 

Last updated :: 03/03/2021, -11:26

Cochin Port Trust has invited e-tenders for lease of 4.05 ha (10 acres) of land at South End Reclamation (SER) Area, W/Island for establishing a Multispecialty Hospital vide e-tender No. MSTC/BLR/COCHIN PORT TRUST/17/WILLINGDON ISLAND/19-20/19365 dated 31.10.2019.

Cochin Port will allot the land on lease basis for a period of 30 years to the successful bidder on as-is where-is condition for the project.  The successful bidder shall construct and   operate the facility.

"Hospital"

The proposed facility is indented for treating general public and as a referral hospital for Cochin Port Trust.  The successful bidder (S.B) shall, at all times, reserve a minimum of 50 beds (“Reserved Beds”) and all other facilities like various Specialist O.P.D. services, investigations in O.P.D. and I.P.D., O.P.D. and I.P.D. procedures / surgery, to be made available to the Sponsored Patients of Cochin Port Trust at CGHS rates, at all times on referral as and when required. The reservation of such beds (General ward, single room, A/C room) shall be as per the prevailing CGHS eligibility rules. All matters with reference to the treatment of the Sponsored patients will be regulated by the prevailing CGHS rules.  The medical expenses of the sponsored patients of CoPT will be paid either by CoPT or directly by the patients.

Willingdon Island is the only area available which is located in close proximity to Cochin city and in a serene and calm environment just ideal for an international level hospital and allied infrastructures. Easy access, yet away from all the crowd and pollution of the city should attract such a venture.

Cochin Port holds land in Willingdon Island enough for any international level hospital suitable for Medical Tourism and also benefits the local population.

Tenders are invited for lease of 10 acres of land at W/Island for the project during  November 2019 on upfront payment basis did not fetch any bids. Accordingly, based on demand from the trade, the land has been now tendered on annual lease rent basis on 05/02/2020 with due date of submission of tender on 20/03/2020. No bids were received on the bid due date. 

An EoI was invited on 17.02.2021 with due date of submission on 24.02.2021.  However no proposals were received.

Last updated :: 03/03/2021, -12:51