  INTERNATIONAL SHIP REPAIR FACILITY

Cochin Port Trust has awarded a project for development of an International Ship Repair Facility to the Cochin Shipyard Ltd. (CSL) on 19-9-2012.  The facility is to come up on 41 acres of land on the Western side of Willingdon Island along the Mattancherry channel. 

CSL is investing around Rs.490 crores in the venture. 

The existing ship repair facilities of the Port including the dry dock (66 m x 12.5 m x 4 m), slipway and workshop complex are being taken over by CSL.  CSL will also install a Ship Lift and Transfer System for 6 vessels.  The Ship Lift System would be approx. 120 m long, with a 30 m wide lifting platform, and have capacity to handle light ship weights upto 6,000 tonnes, LOA 130 m and beam 25 m.  

The facility will enable ships visiting Cochin Port to undertake both floating as well as docking repairs. 

Back

  INTERNATIONAL SHIP REPAIR FACILITY

Cochin Port Trust has awarded a project for development of an International Ship Repair Facility to the Cochin Shipyard Ltd. (CSL) on 19-9-2012.  The facility is to come up on 41 acres of land on the Western side of Willingdon Island along the Mattancherry channel. 

CSL is investing around Rs.490 crores in the venture. 

The existing ship repair facilities of the Port including the dry dock (66 m x 12.5 m x 4 m), slipway and workshop complex are being taken over by CSL.  CSL will also install a Ship Lift and Transfer System for 6 vessels.  The Ship Lift System would be approx. 120 m long, with a 30 m wide lifting platform, and have capacity to handle light ship weights upto 6,000 tonnes, LOA 130 m and beam 25 m.  

The facility will enable ships visiting Cochin Port to undertake both floating as well as docking repairs. 